Vertical Lathe Factory Acceptance Test (FAT) Before Shipment

This article outlines the complete Factory Acceptance Test (FAT) workflow for heavy‑duty CNC vertical lathes before shipment. It focuses on document confirmation, configuration audit, test management, acceptance report requirements and pre‑shipping preparation. Targeted at purchasing managers and project stakeholders, this guidance helps reduce cross‑party disputes, clarify acceptance boundaries and control project delivery risks. Note that FAT performed at the manufacturer’s factory cannot replace the on‑site SAT acceptance after equipment arrival and installation.


A Factory Acceptance Test, known as FAT, is a critical checkpoint before a CNC vertical lathe leaves the manufacturer’s workshop. This procedure confirms that the machine matches the agreed‑upon specification list, runs correctly and comes with all required technical documentation. For heavy‑duty vertical lathes used for flanges, ring‑shaped parts and large housing components, a well‑defined FAT plan greatly reduces misunderstandings between buyers and machine suppliers.

Before the formal FAT starts, both parties need to confirm a complete set of reference documents. These files include the final machine configuration, optional accessories, technical agreement drawings, trial workpiece requirements, measuring tools, report templates and video recording rules. Pre‑agreed standards prevent unexpected arguments after machine assembly is finished.

The first FAT stage is visual and configuration verification. Inspectors cross‑check the machine nameplate, CNC system, tool post, milling units, safety guards, lubrication and cooling packages against the contract. Every optional feature written in the purchase agreement must be physically confirmed on the machine.

Next, technicians carry out no‑load running tests. Operators start the whole control system, run the rotary table at different speeds, move each axis through its full travel range and verify emergency‑stop and safety interlock functions. All auxiliary systems such as lubrication and chip removal equipment are checked during this idle cycle.

Custom optional functions will be tested separately. Automatic tool change, power milling heads and special machining cycles need independent validation. Clients can record key test videos for internal project approval, though video records cannot replace the official signed acceptance report.

Trial cutting forms the core verification step of the FAT process. Machining tasks and tolerance values strictly follow the pre‑signed test scheme. Only the dimensions defined in the technical agreement will be measured for final judgment.

Once all mechanical and cutting tests pass, both sides fill out the formal FAT acceptance report. This document records test dates, machine serial numbers, inspection items, measurement data, rectification records and the final release decision. Remote FAT acceptance via live stream and electronic signatures is also acceptable if agreed in advance.

After the FAT report is signed, the machine is prepared for transportation. Workers clean cutting chips, apply anti‑rust coating on exposed metal surfaces, lock moving parts for transit and pack spare tools and operation manuals. Photographs are kept for delivery tracking.

We recommend buyers prepare a standardized FAT checklist at the contract stage. The checklist covers configuration audit, safety inspection, no‑load movement, optional function verification, trial cutting measurement, document archiving and pre‑shipping packaging.

Please note that factory FAT is not equal to Site Acceptance Test (SAT). SAT will be performed on‑site after equipment arrives at your workshop, including re‑leveling, pipe connection and final commissioning.

If you are sourcing machine tools for large rotary component manufacturing, you can review our vertical lathe and vertical turning milling machine solutions. A customized FAT scheme should always be prepared together with your technical contract and test‑piece drawing for each individual project.